"Uzbekistan Airports" reported that the outage did not affect aircraft take-offs and landings, and all services operated in their usual mode. The departure and arrival halls were supplied with electricity using backup diesel generators and UPS. By 2:49 AM, the power supply was fully restored.

According to "Regional Electric Networks" JSC, a malfunction occurred in the 35 kV high-voltage "Airport-5" network belonging to Uzbekistan Airports, which originates from the "Kuylik" substation. As a result, a power outage occurred at Tashkent airport. During this time, all networks belonging to "Regional Electric Networks" JSC were in good working condition.

At 2:49 AM, the airport was provided with electricity through the consumer's backup networks.