A new overpass was tested for strength in Tashkent

    Cities 7 November 2023 3366

    A test was conducted in the capital following the results of the first stage of construction and installation works of the overpass connecting Babur Street and Tashkent International Airport.

    "During the test, 4 military tanks (40 tons each) were loaded into 4 trailers (35 tons each), thereby the total load on the overpass was 300 tons," the press service of the Ministry of Transport said.

    According to the test results, the overpass successfully withstood the load exceeding the permissible during operation, which indicates its endurance.